The clubhouse renovation is back on track after the storm ruined our end of September completion. The following is the to do list for the project. We are now shooting for end of October, weather permitting.

  1. Playground curbing and mulch were installed in the last few days. We are not completely happy with the work product and need to follow up with our vendor.
  2. Pool fence and playground fence will go in late this week.
  3. Pool scope will start this coming week and be complete by months end. We will not be able to fill it until mid October at the earliest. Fencing needs to be completed first.
  4. The sports court is scheduled to start this week. Lights for the court are scheduled to be delivered this week as well.
  5. Landscaping can be completed around each area as other trades clear out.
  6. We will remove the ugly tree on the Lake bank behind the clubhouse on Tuesday when the other trees are removed. 
  7. Paving in parking lot will occur last in mid October right before or right after the furniture delivery scheduled for the 16th along with the fitness equipment.
  8. The interior spaces are coming along well and punch lists are being created.
  9. Still to be addressed are Comcast service, door access equipment installed, fob logistics, etc.